Question
Download Solution PDFA, B and C together can complete a work in 5 days. A and B together can complete the same work in 6 days. C alone can finish the same work in how many days?
Answer (Detailed Solution Below)
Detailed Solution
Download Solution PDFGiven:
A, B and C together can complete a work in 5 days.
A and B together can complete the same work in 6 days.
Concept used:
Efficiency = (Total work / Total time taken)
Efficiency = work done in a single day.
Calculation:
Let total work is 1
A, B and C together can complete in 1 day is 1 / 5 part
A and B together can do in 1 day 1 / 6 part
So, C can do in one day ,
(A, B and C together can complete in 1 day - A and B together can do in 1 day )
1 / 5 - 1/ 6
⇒ \({6 - 5}\over 30\)
⇒ 1 / 30
∴ C can do the total work in 30 days
Last updated on May 28, 2025
-> SSC MTS 2025 Notification will be released by the Staff Selection Commission (SSC) on the official website on 26th June, 2025.
-> The online application process will also begin once the official notification is out. The last date to apply online will be 25th July 2025 as per the SSC Exam Calendar 2025-26.
-> The selection of the candidates for the post of SSC MTS is based on Computer Based Examination.
-> Candidates with basic eligibility criteria of the 10th class were eligible to appear for the examination.
-> Candidates must attempt the SSC MTS Mock tests and SSC MTS Previous year papers for preparation.