Question
Download Solution PDFPessimistic time and optimistic time of completion of an activity are given as 10 days and 4 days respectively, the variance of the activity will be
Answer (Detailed Solution Below)
Detailed Solution
Download Solution PDFConcept:
Project Evaluation and Review Technique (PERT) is probabilistic in nature and is based upon three-time estimates to complete an activity.
Optimistic Time (to): It is the minimum time that will be taken to complete an activity if everything goes according to the plan.
Pessimistic Time (tp): It is the maximum time that will be taken to complete an activity when everything goes against the plan.
Most likely time (tm): It is the time required to complete a project when an activity is executed under normal conditions.
Average or most expected time is given by
The variance gives the measure of uncertainty of activity completion. The variance of the activity is given by
Variance,
Standard duration,
Calculation:
Given:
tp = 10 days, to = 4 days
The variance of the activity is 1.
Last updated on May 19, 2025
-> JKSSB Junior Engineer recruitment exam date 2025 for Civil and Electrical Engineering has been released on its official website.
-> JKSSB JE exam will be conducted on 10th August (Civil), and on 27th July 2025 (Electrical).
-> JKSSB JE recruitment 2025 notification has been released for Civil Engineering.
-> A total of 508 vacancies has been announced for JKSSB JE Civil Engineering recruitment 2025.
-> JKSSB JE Online Application form will be activated from18th May 2025 to 16th June 2025
-> Candidates who are preparing for JKSSB JE can download syllabus PDF from official website of JKSSB.
-> The candidates can check the JKSSB JE Previous Year Papers to understand the difficulty level of the exam.
-> Candidates also attempt the JKSSB JE Mock Test which gives you an experience of the actual exam.