Which one of the following is NOT considered for the estimation of activity duration?

This question was previously asked in
UPSC ESE (Prelims) Civil Engineering 19 Feb 2023 Official Paper
View all UPSC IES Papers >
  1. Evaluate activities one at a time, independently of all others.
  2. For each activity, assume a normal level of manpower and or equipment.
  3. If time units of working days are being used, assume an exceptional day with maximum working hours.
  4. Normal weather conditions is considered for the estimation of duration of each activity.

Answer (Detailed Solution Below)

Option 3 : If time units of working days are being used, assume an exceptional day with maximum working hours.
Free
ST 1: UPSC ESE (IES) Civil - Building Materials
20 Qs. 40 Marks 24 Mins

Detailed Solution

Download Solution PDF

Explanation:

Estimation of Activity Duration or Time Estimation:

  • A project is composed of many diversified activities which contribute to its completion.
  • An important characteristic of any project is its duration. As its effectiveness and economy are often dependent on the project duration.
  • The total project duration depends on the time taken by each activity.
  • Estimation of time required for any activity requires wide experience of similar activities.
  • Evaluate activities one at a time, independently of all others.
  • For each activity, assume a normal level of manpower and or equipment.
  • If time units of working days are being used, assume a normal workday.
  • Normal weather conditions are considered for the estimation of the duration of each activity.
  • Estimation of these time estimates can be done in two ways:
  1. Deterministic approach: The Planner has enough knowledge about the activity and gives a single estimate of the duration which is almost accurate.
  2. Probabilistic Approach: The planner does not have much idea about the activity as there is little or no past history about it. The limits within which the duration will lie are estimated.
  • The time estimate of an activity has a greater range of variation and hence greater uncertainty. therefore probabilistic approach is used.
  • Time estimate of an activity has a narrow range of variation and hence in this case time estimate is deterministic.
  • PERT follows the probabilistic approach and absorbs the uncertainties into the time estimates for activity and project durations.
  • CPM follows the deterministic approach.

​Hence option (3) is correct.

Latest UPSC IES Updates

Last updated on Jul 2, 2025

-> ESE Mains 2025 exam date has been released. As per the schedule, UPSC IES Mains exam 2025 will be conducted on August 10. 

-> UPSC ESE result 2025 has been released. Candidates can download the ESE prelims result PDF from here.

->  UPSC ESE admit card 2025 for the prelims exam has been released. 

-> The UPSC IES Prelims 2025 will be held on 8th June 2025.

-> The selection process includes a Prelims and a Mains Examination, followed by a Personality Test/Interview.

-> Candidates should attempt the UPSC IES mock tests to increase their efficiency. The UPSC IES previous year papers can be downloaded here.

Hot Links: teen patti earning app teen patti master 2023 teen patti real