CPM MCQ Quiz - Objective Question with Answer for CPM - Download Free PDF

Last updated on Jun 25, 2025

Latest CPM MCQ Objective Questions

CPM Question 1:

The artificial activity which indicates that an activity following it, cannot be started unless the preceeding activity is completed, is known as

  1. event
  2. free float
  3. dummy
  4. constraint

Answer (Detailed Solution Below)

Option 3 : dummy

CPM Question 1 Detailed Solution

Explanation:

The Artificial Activity Indicating Dependency

  • The artificial activity in project scheduling is known as a dummy activity.

  • Dummy activities do not consume time or resources but are used to show logical relationships between activities.

  • They are often represented as dashed lines in network diagrams.

  • A dummy activity ensures that an activity cannot start until the preceding activity is completed.

  • Option 3 (Dummy) is the correct answer.

  • The other options, such as event, free float, and constraint, do not accurately describe this artificial activity.

  • Dummy activities are essential for maintaining logical accuracy in project planning and scheduling.

  • They are commonly used in critical path method (CPM) diagrams to illustrate dependencies.

CPM Question 2:

Which of the following conclusions is/are correct in relation to the given network diagram?

3-5-2025 IMG-1200 Ashish Verma -6

(i) Activity B is controlled by activity A.

(ii) Activity D is controlled by both activities A and C.

(iii) Activity B is independent of activity C.

  1. Only (i) and (iii) are correct.
  2. Only (i) is correct.
  3. Only (i) and (ii) are correct.
  4. All the conclusions are correct.

Answer (Detailed Solution Below)

Option 2 : Only (i) is correct.

CPM Question 2 Detailed Solution

Explanation:

Activity A → B: Solid arrow means B can only start after A ends ⇒ B is dependent on A.

Activity C → D: Solid arrow means D can only start after C ends ⇒ D is dependent on C only.

Dummy C → B: Dummy arrow shows logical dependency ⇒ B is also dependent on C.

(i) Activity B is controlled by activity A – Correct

(ii) Activity D is controlled by both A and C – Incorrect (only C controls D)

(iii) Activity B is independent of activity C – Incorrect (dummy from C to B shows B depends on C)

CPM Question 3:

A critical activity in a project is estimated to take 15 days to complete at a cost of Rs. 30,000. The activity can be expedited to complete in 12 days by spending a total amount of Rs. 54,000. Consider the statements P and Q.

P: It is economically advisable to complete the activity early by crashing if the indirect cost of the project is Rs. 8,500 per day.

Q: It is economically advisable to complete the activity early by crashing, if the indirect cost of the project is Rs. 10,000 per day.

Which one of the following options is CORRECT?

  1. P is true and Q is false
  2. Both P and Q is false
  3. P is false and Q is true
  4. Both P and Q are true

Answer (Detailed Solution Below)

Option 4 : Both P and Q are true

CPM Question 3 Detailed Solution

Explanation:

Given Data:

  • Normal duration: 15 days

  • Normal cost: Rs. 30,000

  • Crashed duration: 12 days

  • Crashed cost: Rs. 54,000

  • Indirect cost: Rs. 8,500 per day (for P) and Rs. 10,000 per day (for Q)

Cost slope (Crashing cost per day) is given by:

\(\mathrm{C} / \mathrm{s}=\frac{54000-30000}{15-12}=8000 \mathrm{Rs} / \text { day }\)

Crashing is economically beneficial if the savings in indirect cost per day exceed the direct cost of crashing per day.

  • If the indirect cost per day is Rs. 8,500 (Statement P):
    Since Rs. 8,500 > Rs. 8,000, it is economically advisable to crash. So, P is true.

  • If the indirect cost per day is Rs. 10,000 (Statement Q):
    Since Rs. 10,000 > Rs. 8,000, it is also economically advisable to crash. So, Q is true.

CPM Question 4:

The direct cost of a project with respect to normal time will be

  1. minimum
  2. maximum
  3. zero
  4. infinity

Answer (Detailed Solution Below)

Option 1 : minimum

CPM Question 4 Detailed Solution

Explanation:

In project management, normal time refers to the planned or standard duration needed to complete a project or an activity without expediting or crashing. During this period, the project operates under normal conditions, without any additional resources or acceleration.

The direct cost of a project typically includes labor, materials, and equipment costs. When a project is completed within the normal time, these costs are usually minimized because:

  • There is no need for overtime or additional shifts.

  • Standard resources are used without any premium charges.

  • There is no need to expedite materials or equipment, which could increase costs.

However, if the project timeline is shortened (crashed), the direct costs increase due to additional expenses to speed up the work. Therefore, the direct cost of a project is at its minimum when completed within normal time.

CPM Question 5:

The time with which direct cost does not reduce with the increase of time is known as

  1. crash time
  2. normal time
  3. optimistic time
  4. between normal time and crash time

Answer (Detailed Solution Below)

Option 2 : normal time

CPM Question 5 Detailed Solution

Explanation:

Direct Project cost:

(i) It is the cost that is directly dependent on the amount of resources involved for the completion of activities. It includes labour, materials, plants, and machining.

(ii) To get the same work done in less time, we have to increases the amount of labor, equipment, and time-saving material that too at extra charges which simply means increases indirect cost.

(iii) The project has the highest cost corresponding to the crash duration and has normal cost corresponding to the normal duration.

Normal time:

(i) Normal time is the standard time that an estimator would usually allow for an activity.

(ii) It is the time with which direct cost does not reduce with the increase in time.

Crash time:

(i) Crash time is the minimum possible time in which an activity can be completed, by employing extra resources.

(ii) Crash time is that time, beyond which the activity cannot be shortened by an amount of increases in the resources.

Top CPM MCQ Objective Questions

A PERT network has 9 activities on its critical path. The standard deviation of each activity on the critical path is 3. The standard deviation of the critical path is

  1. 3
  2. 9
  3. 81
  4. 27

Answer (Detailed Solution Below)

Option 2 : 9

CPM Question 6 Detailed Solution

Download Solution PDF

Concept:

In CPM:

The standard deviation of critical path:

σcp \(\sqrt {Sum\;of\;variance\;along\;critical\;path} \)

σcp\(\sqrt {σ _1^2 + σ _2^2 + \ldots + σ _8^2 + σ _9^2} \)

Where, σ1, σ2, ...., σ8, σ9 are the standard deviation of each activity on the critical path   

Calculation:

Given:

σ1, σ2, ...., σ8, σ9 = 3

σcp = \(\sqrt {σ _1^2 + σ _2^2 + \ldots + σ _8^2 + σ _9^2} \)

σcp\(\sqrt {3^2 + 3^2 + 3^2 + 3^2 + 3^2 + 3^2 + 3^2 + 3^2 + 3^2} \)

σcp\(\sqrt {9 \times 9} \) = 9

∴ the standard deviation of the critical path is 9.

Fulkerson’s rule is connected with the

  1. numbering of event in PERT/CPM
  2. creation of a parallel activity
  3. queueing theory
  4. elimination of dummy activity

Answer (Detailed Solution Below)

Option 1 : numbering of event in PERT/CPM

CPM Question 7 Detailed Solution

Download Solution PDF

Explanation

  • Fulkerson’s rule is used for numbering events involved in the project scheduling network.
  • Types of network diagram
    • Event on the node ( EON )
    • Activity on the node ( AON )

Important Points

  • Hungarian  method – Assignment problems
  • Johnson's  rule – scheduling jobs 
  • Simplex method -  linear programming

The difference between EST of succeeding activity and EFT of the activity under consideration is called

  1. Total float
  2. Independent float
  3. Interfering float
  4. Free float

Answer (Detailed Solution Below)

Option 4 : Free float

CPM Question 8 Detailed Solution

Download Solution PDF
Explanation:

Early Start Time:

  • The earliest point in the schedule at which a task can begin.
  • EST = \(T_E^i\)

Early Finish Time:

  • The earliest point in the schedule at which a task can finish.
  • EFT = \(T_E^i\) + tij

Latest Start Time:

  • The latest point in the schedule at which a task can start without causing a delay.
  • LST = \(T_L^j\) - tij

Latest Finish Time:

  • The latest point in the schedule at which a task can finish without causing a delay.
  • LFT = \(T_L^j\)

Types of float:

1) Total float:

  • It is the difference between the maximum time available and the actual time required for the completion of the activity. or It is the difference between the time available for an activity performance and the duration of the activity.
  • FT = LST - EST = LFT - EFT = \(T_L^j - T_E^i - t_e^{ij}\) 

2) Free float:

  • It is the amount of time by which an activity can be delayed without affecting the EST of the succeeding activity.
  • FT = \(T_E^j - T_E^i - t_e^{ij}\)

3) Independent float:

  • It is the excess of minimum available time over the required activity duration
  • FI = \(T_E^j - T_L^i - t_e^{ij}\) 

4) Interfering float

  • It is the difference between the total float and the free float of an activity.
  • FIN = FT - FF

The time with which direct cost does not reduce with the increase in time is known as

  1. Crash time
  2. Optimistic time
  3. Normal time
  4. Standard time

Answer (Detailed Solution Below)

Option 3 : Normal time

CPM Question 9 Detailed Solution

Download Solution PDF

Explanation:

Direct Project cost:

(i) It is the cost that is directly dependent on the amount of resources involved for the completion of activities. It includes labour, materials, plants, and machining.

(ii) To get the same work done in less time, we have to increases the amount of labor, equipment, and time-saving material that too at extra charges which simply means increases indirect cost.

(iii) The project has the highest cost corresponding to the crash duration and has normal cost corresponding to the normal duration.

Normal time:

(i) Normal time is the standard time that an estimator would usually allow for an activity.

(ii) It is the time with which direct cost does not reduce with the increase in time.

Crash time:

(i) Crash time is the minimum possible time in which an activity can be completed, by employing extra resources.

(ii) Crash time is that time, beyond which the activity cannot be shortened by an amount of increases in the resources.

The excess of minimum available time over activity duration is called

  1. total float
  2. free float
  3. independent float
  4. None of the above

Answer (Detailed Solution Below)

Option 3 : independent float

CPM Question 10 Detailed Solution

Download Solution PDF

Explanation:

Float:

(i) It is associated with activity times.

(ii) It is analogous to the slack of events in PERT.

(iii) It is the range within which the start or finish time of activity may fluctuate without affecting the project completion time.

(iv) Floats are of the following types:

1. Total float: The time span by which starting or finishing of an activity can be delayed without delaying the completion of the project. Total float of activity affects total float of succeeding as well as preceding activities. 

2. Free float: The delay can be made without delaying succeeding activities. It affects only preceding activities.

3. Independent Float: It is the minimum excess available time which exists without affecting any of succeeding or preceding activities.

4. Interfering Float: It is similar to head event slack.

Which one of the following does have some limitations when applied to detailed engineering design work during early stages of a project?

  1. CPM
  2. PERT
  3. Dummy activity
  4. Estimate

Answer (Detailed Solution Below)

Option 1 : CPM

CPM Question 11 Detailed Solution

Download Solution PDF

Concept

Dummy Activity: An activity that is used to maintain the predefined precedence relationship only during the construction of the project network is called a dummy activity.

Estimate: An approximate calculation or judgment of value

PERT is preferred when there are some uncertainties in the methodology, availability of materials, and the final answer is not clearly known.

Whereas CPM is applied when things are almost certain

For example in the case of a construction project, once the project has been finalized there is little doubt of men, material, and equipment required, time, etc. then PERT is used

∴ CPM has limitations in the early stage of the project.

Gantt charts indicate

  1. Comparison of actual progress with the scheduled progress
  2. Balance of work to be done
  3. Progressive cost of project
  4. Inventory costs

Answer (Detailed Solution Below)

Option 1 : Comparison of actual progress with the scheduled progress

CPM Question 12 Detailed Solution

Download Solution PDF

Gantt charts are mainly used to allocate resources to activities. The resources allocated to activities include staff, hardware, and software. Gantt charts are useful for resource planning. A Gantt chart is a special type of bar chart where each bar represents an activity. The bars are drawn along a timeline. The length of each bar is proportional to the duration of time planned for the corresponding activity.

RRB JE CE 9 12Q 76thAug 2015 Shift3 Hindi images Q2

In a CPM network Earliest start time for an event i is 10 weeks. Activity i - j takes 4 weeks for Completion. Event J starts after 16 weeks. Total Float for activity i - j is

  1. 6 weeks
  2. 12 weeks
  3. 10 weeks
  4. 2 weeks

Answer (Detailed Solution Below)

Option 4 : 2 weeks

CPM Question 13 Detailed Solution

Download Solution PDF

Concept:

F1 Shraddha Abhishek 21.9.2021 Correction 2

Total float: It is the amount of time that the completion time of an activity can be delayed without affecting project completion time.

Mathematically, Total Float = (Lj - Ei) - tij

Calculation:

∴ Total Float = (Lj - Ei) - tij = 16 - 10 - 4 = 2 week

Additional Information

Free float: It is the amount of time that the activity completion time can be delayed without affecting the earliest start time of the immediate successor activities in the network.

Mathematically, Free Float = (Ej - Ei) - tij

Independent Float: Amount by which an activity can be delayed without delaying the project; even if all predecessors are at Late Finish and all Successors are at Early Start.

Mathematically, Independent Float = (Ej - Li) - tij

In a bar chart the vertical axis represents

  1. Time
  2. Types of activities
  3. Number of labors
  4. Various activities of the project

Answer (Detailed Solution Below)

Option 4 : Various activities of the project

CPM Question 14 Detailed Solution

Download Solution PDF

Bar Chart / Gantt Chart

First introduced by Hennery Gantt in 1910. Each bar represents a specific job or activity and length of the bar represent the time of completion of that activity. The starting and ending of the bar represent the starting and beginning of that activity.

346899753

CPM Network is updated

  1. Whenever there is difference in the planned and actual performance
  2. At regular intervals
  3. At any times
  4. At fixed times

Answer (Detailed Solution Below)

Option 1 : Whenever there is difference in the planned and actual performance

CPM Question 15 Detailed Solution

Download Solution PDF

Concept:

  • Critical Path Methods (CPM) have been used for planning scheduling and control in construction project management.
  • It is activity oriented method.
Sl. No. CPM PERT
1. Critical path method Program valuation and review technique
2. Deterministic Probabilistic
3. Control time and cost Control only time
4. Activity oriented Event oriented
5. One time estimate Three-time estimate
6. Use- Non research Research

CPM Network is updated whenever there is a difference in the planned and actual performance.

Get Free Access Now
Hot Links: teen patti real teen patti diya teen patti casino